January 23rd
On January 23rd, I did some
draught proofing on the observatory. I had some mMylar sheet which I cut
into strips to go around the joints between the roof and walls. They
were nailed in place to help prevent draughts and insects.
|
|
|
|
|
While the
observatory is mostly complete, other than some internal fittings,
lighting and possible warm room, the strip of land on which it stands is
still incomplete. I'll continue the story of the garden landscaping
until the whole area is complete.
Garden Railway and
Lawn
March 7th
I haven't used the
observatory much over the winter. It has either been raining, overcast
or too cold for my old bones. I've also not had much energy to go out
due to working so hard in the garden. On the 7th, I did do a little wide
field photography of the Jupiter/Venus conjunction. It was one of the
few rare evenings of partially clear sky.
|
|
March 21st
On the 21st, we had 6 tons of
top soil, slate and gravel delivered onto the drive. I didn't fancy
pushing dozens of wheelbarrow loads, 200 feet down our gravel driveway
to the back garden, so split the loads into slightly smaller bags and
used the crane on my WW2 Dodge truck to lift and move it all to the back
garden.
|
|
|
March 25th
On the 25th, all the
arrangements were in place to collect the railway parts for the garden
feature. I returned from a local preservation line with seven sleepers,
rail chairs, screws and enough rail to make about 16 feet of track.
|
|
March 26th
On the 26th, we started
spreading slate around the veggie planters and behind the observatory.
There's two to three inches over the top of a weed membrane to help to
prevent unwanted growth. While there's a small negative impact of the
slate creating unwanted thermals from soaking up solar heat, if I'm
planning a summer session, opening the roof will shade the slate from
the sun. I doubt it will gain enough heat in Autumn, Winter and Spring
to have much effect.
|
|
|
April
3rd
By April 3rd, we were making
good progress on levelling the earth for the new lawn and for the
railway track bed. There's still a bit more work before the final
surface. |
|
April 18th
It was a hard day's work
digging out high spots and filling in low areas with a combination of
earth and gravel for the track bed. This area is now looking pretty good
as far as surface preparation is concerned.
|
|
I now need to work on
levelling the sleeper edging between the lawn and trackbed ( shown laid
in place ). There will be a slight gravel slope down from the sleepers
to the trackbed to account for the different heights of the track and
lawn. There will be further sleepers that run parallel to the hawthorn
hedge to form an edge to a pathway. This will allow steps to be used
when trimming the hawthorn. |
|
April 19th
The 19th saw more weed
clearing and earth moving. The earth for the first two sleepers,
separating the new lawn and railway, was levelled and the sleepers laid
in place. They are not staked down yet, as I want a weed membrane laid
below the sleepers and across the railway trackbed. So until all the
earth moving is complete, I don't want enything permanently fixed in
place.
April 20th & 21st
The 20th was spent clearing
weeds, loose earth and plant matter left over from the woodland to get
down to solid earth. On the 21st, I began excavating parallel to the
hedge for the lawn edging sleepers. They still need further lowering to
match up with the railway/lawn dividing sleepers. It is heavy clay soil
and was slow going, having to cut through tree roots and stones ranging
from pebbles to half bricks left over from the old air raid shelters.
Towards the end of the day, I
brought the additional edging sleepers down from the workshop patio to
the bottom of the garden ready for use. I laid them out along the track
bed to get a feel for the look of the railway and the space around the
track for the crossing gate.
|
|
|
|
|