May 30th
On the 30th, I got all the proper railway sleepers jetwashed, to get rid of plant growth, dirt, oil and soot. This was to allow them to be treated with an oil based preservative.
May 31st
The following day, I managed to get each sleeper loaded onto the wheelbarrow and trundled down the garden to the trackbed. While loading and unloading, I almost gave birth to several of my internal organs. I'm guessing the sleepers are oak, are incredibly dense and weigh a ton! They were still a bit damp from washing, so I left them to dry.
I salvaged some of the old weed membrane that we pulled up and got the decorative sleepers along the hawthorn finished.
|
|
|
|
|
The three sleepers across the front of the gate were also pinned down and screwed together.
I had to redrill one of the pinning holes, as it fell directly in line
with the air raid shelter bricks underground. To hide the odd spacing of
the pins, the sleepers will be capped by some three quarter inch planking,
which will help to tie them together, since they are only a single
layer.
With that done, the railway sleepers were now dry enough to start treating.
Several of them have some quite rotten areas; after all, they were removed as they were no longer servicable. I picked the best side to be the upper face. The underside was given two coats of black bitumen, to help to water proof the surface touching the ground. Once fully dry, the top, sides and ends will be treated with dark brown "Creocote"; an oil based, environmentally friendly version of Creosote. Let's hope they haven't taken all the stuff that works out of
it. Once they are painted and dry, I'll be in a position to start laying
rail!
|
|
|
|
|
On the 1st of June, I took a day off from the railway to do some
pointing work on the patio.
|
June 2nd
I got back to the sleepers on
Friday 2nd. The sleepers were turned so that the sides could be treated
with the Creocote. They were turned again for the upper face and once
more for the other side. In some places, it soaked in quite quickly so
further coats were added in these areas.
|
|
|
I also dragged some more earth from the pile to under the right edge of
the weed barrier, to allow the sleepers to be positioned a little
further away from the gate. In the picture with all seven sleepers laid
out, they've been spaced out pretty much to their final positions. A
yellow steel tape measure can be seen along the left side of the
sleepers, which is the approximate length of the rail.
I ran out of bitumen the
other day and have some more on order. Once it's here, I plan on
painting the sides and ends of the sleepers to at least half their
height, to help waterproof the lower portions, as I don't want to be
digging out the ballast regularly to re-treat the wood. Later in the
day, after the temperature dropped a bit, I pulled the trailer out and
unloaded all the R/C aircraft. This was to allow me to remove the four
pieces of rail from the back of the box.
There are two 9 feet long
sections and two pieces at 7 feet 6 inches. They are HEAVY; and I
thought the sleepers were heavy! If they are 100 to 130 pound rail, the
longest pieces could be up to almost 400 pounds in weight.
|
|
Using some wooden levers, the
rails were moved to the front edge of the trailer. Tie-down straps were
wrapped around the rail and a piece of wood as a handle and they were
dragged out to the edge of the drive. I think I'll make some wooden 'A'
frames with lifting straps, to 'walk' the rails down the garden, rather
than trying to lift them.
|
|
June 3rd
On the 3rd, the sleepers were
treated again with the Creocote wood treatment and left to dry.
|
|
On the 4th, I painted three
quarters of the way up the sides and ends of the sleepers with bitumen
to help waterproof them. I also painted the footprints where the rail
chairs sit, as water could gather under there.
|
|
On the 6th, I collected the
steel for the second gatepost mount and welded up the parts. Late in the
day, the inside, outside and upper surfaces were painted in Hammerite.
|
June 7th
On the morning of the 7th, I
painted the gatepost mount a second coat of Hammerite over all the areas
that had been already painted. Once cured, it can be turned over and the
underside can be painted. I also painted the anchor bolts that hold the
main gatepost onto its concrete footing. After lunch, I began to
transport rail chairs from the garage to the trackbed. Two chairs at a
time, plus six chair screws was as much as I could carry in the
wheelbarrow. They are very heavy.
While there were already
holes in the sleepers from previous chair screws, they were very tight
to screw in, especially the last couple of inches. Even with the two
feet long wrench, it took two hands and a lot of force to get the screws
all the way home. Actually, I left them with about a sixteenth of an
inch of play, to allow the chair to move slightly on the sleeper. This
should help with alignment once I drop the rail into the top of the
chairs. It took most of the afternoon to transport the chairs and to get
them screwed down.
|
|
|
|
|