Sun  -  Moon  -  Planets  -  Comets & Small Solar System Bodies  -  Messier Objects  -  NGC & IC Objects  -  Events, Widefield & Montages  -  Stars  -  Telescope

The New Pinetree Observatory Build - 2022

The new house had a big garden with woodland either side towards the bottom. The first picture shows one of the small woodlands and the camera is looking South. If the trees were cleared, the patch of ground was ideal for a new observatory with a good Southern view and a fairly clear horizon. Picture two shows the plan for the new dual pier observatory, modified from a 12 x 8 feet shed. The trees were cleared in the Spring of 2021, which also improved the light to the bottom of the garden, but no further work was done until April 9th 2022. That's when the weed and earth clearing began, approximately 3 inches of earth, down to the original weed barrier.
 
 
The approximate position of the corners and piers was plotted out roughly to see how they fell around the tree stumps that remained in the ground. That suggested a slight move of 6 to 8 inches would help to avoid the worst of the stumps and roots. The new position was more accurately plotted out, followed by staking out the shed footings. I then began digging out the footings, discovering the foundations for an old World War 2 air raid shelter. I hoped I wasn't going to find too much concrete still buried.
 
 
The observatory needed ten footings for the basic building and another two for the roof runners. Each hole gave up around a wheelbarrow load of earth.
 
 
In the rear left corner, the was a large lump of concrete inside the footing hole, which I decided to leave it alone. Nearby, shown in the red dotted line, there was a very large piece of concrete from the air raid shelter floor. We tried to dig out until we realised how big it was and buried it again. I suspected the concrete in the foundation hole was also quite big. By April 21st, eight of the holes for the footings were dug out and two 12 inch diameter postal tubes arrived to form the moulds for the piers.
 
 
The tubes were given a couple of coats of dilute waterproof PVA glue to help to seal and strengthen the card in preparation for the concrete pour. Then I started laying the footings which were formed from two high density concrete blocks, bedded on concrete. Wooden posts would be mounted on top of these with metal brackets, which in turn would support the observatory floor. 
 
 
At the end of April 22nd, I balanced the two card piers in place to get a sense of the layout and space. The following day, I did some plotting out of the floor height. The garden slopes, so the floor at one end is quite a bit higher than the other. To help the situation, the footing with the large block of concrete in it, really needed lowering. The only way to achieve this was to use a grinder with a stone cutting disc and slowly, bit by bit, slice and break out parts of the concrete air raid shelter floor. I didn't find the end of the slab, but lowered it enough to drop my footing a bit. The frame supporting the floor will be pretty much touching the ground here, but will be around two feet above the lawn at the other end of the observatory. I'm going to need some steps from the lawn so I can enter. They will probably fold up into the doorway when not needed.
 

PAGE 1 - PAGE 2 - PAGE 3 - PAGE 4 - PAGE 5 - PAGE 6 - PAGE 7 - PAGE 8 - PAGE 9 - PAGE 10 - PAGE 11 - PAGE 12 - PAGE 13 - PAGE 14 - PAGE 15

PAGE 16 - PAGE 17 - PAGE 18 - PAGE 19 - PAGE 20 - PAGE 21 - PAGE 22 - PAGE 23 - PAGE 24 - PAGE 25 - PAGE 26 - PAGE 27

HOME